Korea LG Chem Co., Ltd GS Engineering & Construction Co., Ltd Insulation of LG Chem. Daesan Revamping Project Petrochemical Insulation 2006.12.01~2007.05.01
Korea LG-Caltex Oil Refinery Co., Ltd Inbang Industrial Co., Ltd Insulation of NO.2 HOU Inter-Plant Piping Tie-in Refinery Insulation 2006.12.01~2007.09.01
Korea LG-Caltex Oil Refinery Co., Ltd GS Engineering & Construction Co., Ltd Insulation of NO.2 HOU Project Offsite Area Refinery Insulation 2006.12.01~2007.12.01
Korea Korea Gas Corporation Co., Ltd GS Engineering & Construction Co., Ltd Cryogenic Tank Insulation of Tongyoung LNG Terminal Tank#12 Gas Insulation 2006.12.01~2009.01.01
Korea POSCO Co., Ltd POSCO E&C Co., Ltd Mechanical Work of Pohang No.2 Cold Rolling Mill PCM Ph.8/9 Steel Mill Mech/Piping 2006.11.01~2007.04.01
Korea LGDOW GS Engineering & Construction Co., Ltd LG-Dow Polycarbonate Train-Ⅱ Project Petrochemical Mech/Piping/Stl.Str 2006.10.01~2007.09.01
Korea Korea Midland Power Co., Ltd KEPCO KPS Co., Ltd Maintenance of Seoul Power Plant5 PENT HOUSE & CASING GAS LEAK Power Insulation 2006.09.01~2006.10.01
Korea POSCO Co., Ltd POSCO E&C Co., Ltd Mechanical Work of Pohang FINEX 1 Ph. 10/11/12 Steel Mill Mech/Piping/Stl.Str 2006.08.01~2007.04.01
Korea LG Chem Co., Ltd LG Chem Co., Ltd Insulation Repair Work of Steam Failure Prevention Petrochemical Insulation 2006.07.01~2006.10.01
Korea Korea Midland Power Co., Ltd KEPCO KPS Co., Ltd Insulation Repair Work of Boryung Power Plant 5 Power Insulation 2006.06.01~2006.07.01
Korea POSCO Co., Ltd POSCO E&C Co., Ltd Mechanical Work of Pohang PCM Ph.4/5/6 Steel Mill Mech/Piping/Stl.Str 2006.06.01~2007.02.01
Korea GS Caltex Co., Ltd GS Engineering & Construction Co., Ltd Mechanical Work of No.2 HOU HCR(LP) AREA Refinery Mech/Piping/Stl.Str 2006.05.01~2008.01.01
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Insulation of LG Chem. Daesan Revamping Project 사업분야: Petrochemical 공종: Insulation of LG Chem. Daesan Revamping Project
    기간: 2006.12.01~2007.05.01 계약금액:
  • 지역: Korea 발주처: LG-Caltex Oil Refinery Co., Ltd
    공사명: Insulation of NO.2 HOU Inter-Plant Piping Tie-in 사업분야: Refinery 공종: Insulation of NO.2 HOU Inter-Plant Piping Tie-in
    기간: 2006.12.01~2007.09.01 계약금액:
  • 지역: Korea 발주처: LG-Caltex Oil Refinery Co., Ltd
    공사명: Insulation of NO.2 HOU Project Offsite Area 사업분야: Refinery 공종: Insulation of NO.2 HOU Project Offsite Area
    기간: 2006.12.01~2007.12.01 계약금액:
  • 지역: Korea 발주처: Korea Gas Corporation Co., Ltd
    공사명: Cryogenic Tank Insulation of Tongyoung LNG Terminal Tank#12 사업분야: Gas 공종: Cryogenic Tank Insulation of Tongyoung LNG Terminal Tank#12
    기간: 2006.12.01~2009.01.01 계약금액:
  • 지역: Korea 발주처: POSCO Co., Ltd
    공사명: Mechanical Work of Pohang No.2 Cold Rolling Mill PCM Ph.8/9 사업분야: Steel Mill 공종: Mechanical Work of Pohang No.2 Cold Rolling Mill PCM Ph.8/9
    기간: 2006.11.01~2007.04.01 계약금액:
  • 지역: Korea 발주처: LGDOW
    공사명: LG-Dow Polycarbonate Train-Ⅱ Project 사업분야: Petrochemical 공종: LG-Dow Polycarbonate Train-Ⅱ Project
    기간: 2006.10.01~2007.09.01 계약금액:
  • 지역: Korea 발주처: Korea Midland Power Co., Ltd
    공사명: Maintenance of Seoul Power Plant5 PENT HOUSE & CASING GAS LEAK 사업분야: Power 공종: Maintenance of Seoul Power Plant5 PENT HOUSE & CASING GAS LEAK
    기간: 2006.09.01~2006.10.01 계약금액:
  • 지역: Korea 발주처: POSCO Co., Ltd
    공사명: Mechanical Work of Pohang FINEX 1 Ph. 10/11/12 사업분야: Steel Mill 공종: Mechanical Work of Pohang FINEX 1 Ph. 10/11/12
    기간: 2006.08.01~2007.04.01 계약금액:
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Insulation Repair Work of Steam Failure Prevention 사업분야: Petrochemical 공종: Insulation Repair Work of Steam Failure Prevention
    기간: 2006.07.01~2006.10.01 계약금액:
  • 지역: Korea 발주처: Korea Midland Power Co., Ltd
    공사명: Insulation Repair Work of Boryung Power Plant 5 사업분야: Power 공종: Insulation Repair Work of Boryung Power Plant 5
    기간: 2006.06.01~2006.07.01 계약금액:
  • 지역: Korea 발주처: POSCO Co., Ltd
    공사명: Mechanical Work of Pohang PCM Ph.4/5/6 사업분야: Steel Mill 공종: Mechanical Work of Pohang PCM Ph.4/5/6
    기간: 2006.06.01~2007.02.01 계약금액:
  • 지역: Korea 발주처: GS Caltex Co., Ltd
    공사명: Mechanical Work of No.2 HOU HCR(LP) AREA 사업분야: Refinery 공종: Mechanical Work of No.2 HOU HCR(LP) AREA
    기간: 2006.05.01~2008.01.01 계약금액: