DAEAH E&C is a specialized construction company for plant mechanical equipment.
DAEAH E&C is a specialized construction company for plant mechanical equipment.
Region | Region Owner | Primary Contractor |
Name of Project | Business Field |
Construction Type |
Period | Contract Amount (KRW 1,000) |
---|---|---|---|---|---|---|---|
Korea | Korea Midland Power Co., Ltd | SEA STX NTech Co., Ltd | Boryeong Thermal Power Plant Unit 3 Purchase and installation of environmental facilities (denitrification, dust collection, desulfurization facilities) Machinery demolition and installation work (steel, steel pipe, machinery) | Power | Mech/Piping/Stl.Str | 2018.08.20~2019.06.24 | |
Korea | LG Chem Co., Ltd | D&O Co., Ltd | Chemical Yeosu PPS Pilot Plant Construction Project Mechanical piping steel frame installation work | Petrochemical | Mech/Piping/Stl.Str | 2018.08.13~2018.12.31 | |
Korea | LG Chem Co., Ltd | D&O Co., Ltd | Chemical Yeosu NPC new construction project Mechanical pipe installation steel construction work | Petrochemical | Mech/Piping/Stl.Str | 2018.08.13~2019.02.28 | |
Korea | Samsung Electronics Co., Ltd | Samsung C&T Co., Ltd | E-PJT [Equipment] General piping Area 2 (UT4) | High-Tech | Piping | 2018.07.26~2019.10.31 | |
Korea | LG Chem Co., Ltd | GS Engineering & Construction Co., Ltd | LG Chem 6AA Project (Machinery & Piping Installation Work) | Petrochemical | Mech/Piping | 2018.07.17~2019.05.31 | |
Korea | Korea Hydro & Nuclear Power Co., Ltd | Hyundai Engineering & Construction Co., Ltd | Shinhanwool Nuclear Power Plant 1 & 2 Mechanical / auxiliary equipment and A.C equipment Installation 1section remaining | Nuclear | Mech/Piping | 2018.07.10~2023.09.30 | |
Korea | Korea Midland Power Co., Ltd | Hyundai Rotem Co., Ltd | Boryeong thermal power plant coal handling pier 3 Mechanical Installation (2) | Power | Mech | 2018.06.12~2019.01.31 | |
Korea | Lotte Chemical Co., Ltd | DL Co., Ltd | Lotte H-NC3 Revamping (PKG1) thermal insulation(A section) | Petrochemical | Insulation | 2018.06.11~2018.10.25 | |
Uzbekistan | JSC UZBEKENERGO | Hyundai Engineering Co., Ltd | Uzbekistan Takhiatash Power Plant Efficiency Improvement Project PKG-1(Mechanical Erection & Piping Work) | Power | Mech/Piping | 2018.06.07~2020.07.31 | |
Korea | LG Chem Co., Ltd | D&O Co., Ltd | LG Chem Daesan 3BE Expansion Project (Mechanical / Piping / Steel Structure) | Petrochemical | Mech/Piping/Stl.Str | 2018.05.15~2019.04.30 | |
Korea | Wirye Energy Service Co., Ltd | HJ Heavy Industries Co., Ltd | UIRYE ES Gailil Pneumatic Machine Installation and Piping Construction | ETC | Mech/Piping | 2018.05.03~2018.10.31 | |
Korea | Lotte Chemical Co., Ltd | Hyundai Engineering Co., Ltd | Lotte Chemical PC2 Project / Machinery, Piping, Steel Structure (PKG2) | Petrochemical | Mech/Piping/Stl.Str | 2018.04.27~2020.02.29 |