Region Region Owner Primary
Contractor
Name of Project Business
Field
Construction
Type
Period Contract Amount
(KRW 1,000)
Korea CGN Daesan Electric Power Co., Ltd Hyundai Engineering & Construction Co., Ltd Daesan Biomass Power Plant Construction Insulation Power Insulation 2019.11.15~2021.02.28
Korea Ulsan PP Co., Ltd SK Engineering & Construction Co., Ltd Ulsan PP Project Machinery / Plumbing / EQ Steel Structure (PKG # 3) Petrochemical Mech/Piping/Stl.Str 2019.10.29~2021.04.30
Korea LG Chem Co., Ltd GS Engineering & Construction Co., Ltd Yeosu No.2 Complex Project(Cheonnam)Steel (PKG-2,Module) Petrochemical Stl.Str 2019.10.28~2020.03.31
Korea LG Chem Co., Ltd D&O Co., Ltd Daesan CDC Organic Catalyst Expansion Construction (Pre-Utility Utility Line Construction), Machinery / Plumbing Construction Petrochemical Mech/Piping 2019.10.24~2020.02.29
Korea LG Chem Co., Ltd D&O Co., Ltd Yeosu H-Project, Piping Installation Petrochemical Mech/Piping 2019.10.24~2020.02.29
Korea Samsung Display Co., Ltd Samsung Display Co., Ltd Asan 1FAB Sprinkler Normalization Head Finish Construction High-Tech Piping 2019.10.02~2020.04.30
Korea GS Caltex Co., Ltd GS Engineering & Construction Co., Ltd MFC Project / Area2 Petrochemical Mech/Piping 2019.10.01~2021.03.30
Korea GS EPS GS Engineering & Construction Co., Ltd Dangjin Biomass Power Plant 2 Construction (Chungnam) Machinery & Piping Installation Power Mech/Piping 2019.09.26~2021.01.15
Korea HD Hyundai Oilbank Co., Ltd Hyundai Engineering & Construction Co., Ltd HDO REVAMPING PROJECT (2020) Machinery Piping Steel Section 5 Tool (CRU) Refinery Mech/Piping/Stl.Str 2019.09.20~2020.10.31
Korea LG Chem Co., Ltd GS Engineering & Construction Co., Ltd Yeosu No.2 Complex(Y2C) Project / SMP PKG-1, NCC#1 Petrochemical Mech/Piping 2019.09.05~2020.12.31
Indonesia PT. Cirebon Energi Prasarana (PT. CEPR) Hyundai Engineering & Construction Co., Ltd CIREBON 2 Coal Power Plant Project-Machinery Installation PKG B Power Mech 2019.09.02~2021.12.31
Korea Samsung Display Co., Ltd Samsung Display Co., Ltd Giheung Mask Bldg Old Sprinkler Replacement High-Tech Piping 2019.08.06~2019.12.31
  • 지역: Korea 발주처: CGN Daesan Electric Power Co., Ltd
    공사명: Daesan Biomass Power Plant Construction Insulation 사업분야: Power 공종: Daesan Biomass Power Plant Construction Insulation
    기간: 2019.11.15~2021.02.28 계약금액:
  • 지역: Korea 발주처: Ulsan PP Co., Ltd
    공사명: Ulsan PP Project Machinery / Plumbing / EQ Steel Structure (PKG # 3) 사업분야: Petrochemical 공종: Ulsan PP Project Machinery / Plumbing / EQ Steel Structure (PKG # 3)
    기간: 2019.10.29~2021.04.30 계약금액:
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Yeosu No.2 Complex Project(Cheonnam)Steel (PKG-2,Module) 사업분야: Petrochemical 공종: Yeosu No.2 Complex Project(Cheonnam)Steel (PKG-2,Module)
    기간: 2019.10.28~2020.03.31 계약금액:
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Daesan CDC Organic Catalyst Expansion Construction (Pre-Utility Utility Line Construction), Machinery / Plumbing Construction 사업분야: Petrochemical 공종: Daesan CDC Organic Catalyst Expansion Construction (Pre-Utility Utility Line Construction), Machinery / Plumbing Construction
    기간: 2019.10.24~2020.02.29 계약금액:
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Yeosu H-Project, Piping Installation 사업분야: Petrochemical 공종: Yeosu H-Project, Piping Installation
    기간: 2019.10.24~2020.02.29 계약금액:
  • 지역: Korea 발주처: Samsung Display Co., Ltd
    공사명: Asan 1FAB Sprinkler Normalization Head Finish Construction 사업분야: High-Tech 공종: Asan 1FAB Sprinkler Normalization Head Finish Construction
    기간: 2019.10.02~2020.04.30 계약금액:
  • 지역: Korea 발주처: GS Caltex Co., Ltd
    공사명: MFC Project / Area2 사업분야: Petrochemical 공종: MFC Project / Area2
    기간: 2019.10.01~2021.03.30 계약금액:
  • 지역: Korea 발주처: GS EPS
    공사명: Dangjin Biomass Power Plant 2 Construction (Chungnam) Machinery & Piping Installation 사업분야: Power 공종: Dangjin Biomass Power Plant 2 Construction (Chungnam) Machinery & Piping Installation
    기간: 2019.09.26~2021.01.15 계약금액:
  • 지역: Korea 발주처: HD Hyundai Oilbank Co., Ltd
    공사명: HDO REVAMPING PROJECT (2020) Machinery Piping Steel Section 5 Tool (CRU) 사업분야: Refinery 공종: HDO REVAMPING PROJECT (2020) Machinery Piping Steel Section 5 Tool (CRU)
    기간: 2019.09.20~2020.10.31 계약금액:
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Yeosu No.2 Complex(Y2C) Project / SMP PKG-1, NCC#1 사업분야: Petrochemical 공종: Yeosu No.2 Complex(Y2C) Project / SMP PKG-1, NCC#1
    기간: 2019.09.05~2020.12.31 계약금액:
  • 지역: Indonesia 발주처: PT. Cirebon Energi Prasarana (PT. CEPR)
    공사명: CIREBON 2 Coal Power Plant Project-Machinery Installation PKG B 사업분야: Power 공종: CIREBON 2 Coal Power Plant Project-Machinery Installation PKG B
    기간: 2019.09.02~2021.12.31 계약금액:
  • 지역: Korea 발주처: Samsung Display Co., Ltd
    공사명: Giheung Mask Bldg Old Sprinkler Replacement 사업분야: High-Tech 공종: Giheung Mask Bldg Old Sprinkler Replacement
    기간: 2019.08.06~2019.12.31 계약금액: