Region Region Owner Primary
Contractor
Name of Project Business
Field
Construction
Type
Period Contract Amount
(KRW 1,000)
Korea LG Chem Co., Ltd GS Engineering & Construction Co., Ltd Naju 1-AA restarting construction during construction Petrochemical Insulation 2000.10.01~2001.01.01
Korea LGDOW GS Engineering & Construction Co., Ltd LG DOW PC thermal construction Petrochemical Insulation 2000.10.01~2001.02.01
Korea POSCO Holdings Co., Ltd POSCO E&C Co., Ltd Pohang direction, electric steel sheet rationalization 2/3 construction construction (Mechanical Equipment 2) Steel Mill Mech/Piping 2000.08.01~2001.11.01
Korea Korea Electric Power Corporation Co., Ltd Hyundai Engineering & Construction Co., Ltd Taean Thermal Power #5 and 6 Construction Construction Power Insulation 2000.07.01~2002.07.01
Korea Korea Electric Power Corporation Co., Ltd Daea Construction Co., Ltd Taean Thermal Power #5 and 6 Construction Construction Power Insulation 2000.06.01~2002.07.01
Korea Korea Gas Corporation Co., Ltd Hyundai Engineering & Construction Co., Ltd Cryogenic Tank Insulation Work of Inchon LNG Terminal Tank#11,12 Gas Insulation 2000.05.01~2001.09.01
Korea Korean Oil painting Co., Ltd Korean Oil painting Co., Ltd #1 Factory product warehouse roof material replacement work Petrochemical Mech/Piping 2000.04.01~2000.05.01
Korea Korean Oil painting Co., Ltd Samsung C&T Co., Ltd Insulation Work of KPIC Ulsan Plant Petrochemical Insulation 2000.04.01~2000.07.01
Korea LG Chem Co., Ltd LG Chem Co., Ltd Piping Insulation Work of COMBUSTION AIR DUCT Petrochemical Insulation 2000.04.01~2000.07.01
Taiwan FORMOSA Samsung C&T Co., Ltd Formosa Refinery #2 (DCU, MTBE) Project Refinery Mech/Piping 2000.03.01~2000.07.01
Korea SK Co., Ltd SK Engineering & Construction Co., Ltd Insulation Work of Utility Supply Project Refinery Insulation 2000.03.01~2000.10.01
Taiwan FORMOSA Samsung C&T Co., Ltd Formosa Olefin Project Petrochemical Insulation 2000.03.01~2000.11.01
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Naju 1-AA restarting construction during construction 사업분야: Petrochemical 공종: Naju 1-AA restarting construction during construction
    기간: 2000.10.01~2001.01.01 계약금액:
  • 지역: Korea 발주처: LGDOW
    공사명: LG DOW PC thermal construction 사업분야: Petrochemical 공종: LG DOW PC thermal construction
    기간: 2000.10.01~2001.02.01 계약금액:
  • 지역: Korea 발주처: POSCO Holdings Co., Ltd
    공사명: Pohang direction, electric steel sheet rationalization 2/3 construction construction (Mechanical Equipment 2) 사업분야: Steel Mill 공종: Pohang direction, electric steel sheet rationalization 2/3 construction construction (Mechanical Equipment 2)
    기간: 2000.08.01~2001.11.01 계약금액:
  • 지역: Korea 발주처: Korea Electric Power Corporation Co., Ltd
    공사명: Taean Thermal Power #5 and 6 Construction Construction 사업분야: Power 공종: Taean Thermal Power #5 and 6 Construction Construction
    기간: 2000.07.01~2002.07.01 계약금액:
  • 지역: Korea 발주처: Korea Electric Power Corporation Co., Ltd
    공사명: Taean Thermal Power #5 and 6 Construction Construction 사업분야: Power 공종: Taean Thermal Power #5 and 6 Construction Construction
    기간: 2000.06.01~2002.07.01 계약금액:
  • 지역: Korea 발주처: Korea Gas Corporation Co., Ltd
    공사명: Cryogenic Tank Insulation Work of Inchon LNG Terminal Tank#11,12 사업분야: Gas 공종: Cryogenic Tank Insulation Work of Inchon LNG Terminal Tank#11,12
    기간: 2000.05.01~2001.09.01 계약금액:
  • 지역: Korea 발주처: Korean Oil painting Co., Ltd
    공사명: #1 Factory product warehouse roof material replacement work 사업분야: Petrochemical 공종: #1 Factory product warehouse roof material replacement work
    기간: 2000.04.01~2000.05.01 계약금액:
  • 지역: Korea 발주처: Korean Oil painting Co., Ltd
    공사명: Insulation Work of KPIC Ulsan Plant 사업분야: Petrochemical 공종: Insulation Work of KPIC Ulsan Plant
    기간: 2000.04.01~2000.07.01 계약금액:
  • 지역: Korea 발주처: LG Chem Co., Ltd
    공사명: Piping Insulation Work of COMBUSTION AIR DUCT 사업분야: Petrochemical 공종: Piping Insulation Work of COMBUSTION AIR DUCT
    기간: 2000.04.01~2000.07.01 계약금액:
  • 지역: Taiwan 발주처: FORMOSA
    공사명: Formosa Refinery #2 (DCU, MTBE) Project 사업분야: Refinery 공종: Formosa Refinery #2 (DCU, MTBE) Project
    기간: 2000.03.01~2000.07.01 계약금액:
  • 지역: Korea 발주처: SK Co., Ltd
    공사명: Insulation Work of Utility Supply Project 사업분야: Refinery 공종: Insulation Work of Utility Supply Project
    기간: 2000.03.01~2000.10.01 계약금액:
  • 지역: Taiwan 발주처: FORMOSA
    공사명: Formosa Olefin Project 사업분야: Petrochemical 공종: Formosa Olefin Project
    기간: 2000.03.01~2000.11.01 계약금액: