Region | Region Owner | Primary Contractor |
Name of Project | Business Field |
Construction Type |
Period | Contract Amount (KRW 1,000) |
---|---|---|---|---|---|---|---|
Korea | POSCO Co., Ltd | POSCO E&C Co., Ltd | Gwangyang 3 Blast Furnace Secondary Repair Machine Construction(PCI) | Steel Mill | Piping | 2019.05.02~2020.07.30 | |
Korea | Ulsan PP Co., Ltd | SK Engineering & Construction Co., Ltd | Ulsan PP Project Interconnection Line Construction | Petrochemical | Piping | 2019.04.15~2021.04.30 | |
Korea | SK Energy Co., Ltd | SK Engineering & Construction Co., Ltd | Ulsan S-Project (VRDS) Insulation | Petrochemical | Insulation | 2019.04.15~2020.09.30 | |
Korea | Flowering Corporation | Doosan Mecatech Co., Ltd | LYONDELLBASELL Insulation Installation | ETC | Insulation | 2019.04.10~2019.08.20 | |
Vietnam | Hyosung VINA Chemical Co., Ltd | SGC E-Tech Construction Co., Ltd | VIETNAM OSBL PIPING WORK PP4 PROJECT | Steel Mill | Piping | 2019.04.05~2019.11.30 | |
Korea | GS Power Co., Ltd | GS Engineering & Construction Co., Ltd | Anyang cogeneration power plant No.2 construction mechanical / piping installation | Power | Mech/Piping | 2019.04.04~2021.12.31 | |
Korea | LG Chem Co., Ltd | D&O Co., Ltd | Yeosu CA2 expansion PJT ISBL Mechanical and piping construction | Petrochemical | Mech/Piping | 2019.03.28~2020.03.31 | |
Korea | Korea Midland Power Co., Ltd | SEA STX NTech Co., Ltd | Boryeong Thermal Power Plant Unit 3 environmental facilities (denitrification, dust collection, desulfurization facilities) Purchase and Installation Project insulation work | Power | Insulation | 2019.03.20~2019.09.30 | |
Korea | Goseong Green Power Co., Ltd | SK Engineering & Construction Co., Ltd | Gosung Green Power Project Insutaion Work | Power | Insulation | 2019.03.18~2022.06.30 | |
Korea | Samsung Display Co., Ltd | Samsung Display Co., Ltd | 8-1 line MB Tower DRAIN piping installation work | High-Tech | Piping | 2019.03.12~2019.05.31 | |
Korea | Samsung Display Co., Ltd | Samsung Display Co., Ltd | A4 High-k CVD secondary piping hook up construction | High-Tech | Mech | 2019.03.05~2019.10.31 | |
Korea | POSCO Co., Ltd | POSCO E&C Co., Ltd | Gwangyang 3 Blast Furnace Secondary Repair Machine Installation 3 (Piping) | Steel Mill | Piping | 2019.02.27~2020.07.31 |